urban-projects
Browns Plains Waste Recycling Facility
Client - Logan City Council
Location - Browns Plains, QLD
Value - $5.3M
Start date - Jul 2021
Completion date - Jan 2022
Browns Plains Waste Recycling Facility is an active landfill site that provides recycling and waste management services to the residents of Logan City Council and commercial customers. Logan City Council have engaged SEE Civil to construct Cell 2E (Phase 2) to ensure the required disposal capability is maintained. The Cell to be constructed is approximately 46,900m2.
Logan City Council have also engaged SEE Civil to undertake stormwater upgrade works around the perimeter of the landfill site including culverts, HSE basin and lined drains to capture and treating the stormwater within the site.
Scope of Works
- Clearing and grubbing
- Bulk earthworks (cut to stockpile)
- Subgrade preparation
- Clay liner installation
- Supply and install clay liner, cushion geotextile, strip drain, geo grid and leachate collection pipework
- Instillation of drainage gravel
- Construction of swale drain
- HSE basin construction
- Supply and installation of box culverts
Cedar Grove - Wastewater Treatment Plant
Previous Project
Vantage Yatala
Next Project